What the survey found under the old floor

What the survey found under the old floor

Written by

Lucas Reinhardt

Published on

June 9, 2026

Week three

We lifted the floorboards expecting a suspended timber floor over a ventilated void, because that is what the 1930s drawings showed and what two previous surveys had assumed. We found a concrete slab poured directly onto made ground, no membrane, and a moisture reading that explained the smell everyone had been politely ignoring.

The scope we had priced no longer existed. Neither did roughly a fifth of the budget, which was about to be consumed by work nobody would ever see.

The restored ground floor after the slab was replaced
The same room, fourteen months on. The expensive part is entirely invisible.

The conversation we did not delay

We called the owners that afternoon, from site, before we had a solution. That is against every instinct — you want to arrive with options — but a client who learns about a problem at the same time as the fix has been managed, and knows it.

What we had instead was a photograph, a moisture reading, and three questions we did not yet know the answer to. The call lasted forty minutes and was uncomfortable throughout.

“I would rather be told something frightening on Tuesday than something reassuring that turns out to be wrong in March.”

What we gave up

The new slab, insulation and membrane took the budget that had been earmarked for the rear extension. The owners chose the floor. We drew the extension anyway, dated it, and left it in the file — the drainage and structural provision are in the ground, so it can be built whenever they want it without touching what is finished.

Restoration is mostly this: discovering the building's actual condition and deciding, in public and quickly, what to sacrifice. The projects that go badly are not the ones with surprises. They are the ones where the surprise was managed quietly for a fortnight first.

Lucas Reinhardt

Lucas Reinhardt

Project Architect

Every restoration has a moment where the building tells you the brief was wrong. How you handle that hour decides the whole project.

(before you commit)

Bring us

the

brief

you

doubt

start a conversation →
start a conversation →